Explore Evers & Sons' portfolio of completed work that showcases our expertise in delivering safe, reliable, and high-quality energy infrastructure services for clients nationwide.
6
Service Divisions
5
Integrated Support Services
1
Partner for Your Next EPC Project
4+
Decades of Experience
Decommissioning & Asset Abandonment
VIRGINIA
Facility Demolition: Compressor Station
Hazardous Material Removal and Disposal
Safely removed and disposed of all hazardous building materials, including:
Demolition
Decommissioning & Asset Abandonment
Texas
Facility Demolition: Central Tank Battery
Demolition and Equipment Removal
Demolished all buildings and structures on site, including:
Demolition
Facilities
TEXAS
Compressor Station Expansion
Evers & Sons Inc. provided full-scope construction services to support a brownfield compressor expansion, including concrete, structural steel, mechanical piping, equipment installation, painting, and insulation.
Compression
Maintenance
TEXAS
Compressor Maintenance Upgrade
Evers & Sons Inc. provided maintenance, structural, and piping modifications to support the upgrade of nine compressors within an existing facility.
Compression
Fabrication
TEXAS
Piggable Wye Fitting
Evers & Sons Inc. provided pipe and steel fabrication for pipeline support structures.
Specialty
Pipeline
TEXAS
12″ Pipeline Capacity Expansion
Evers & Sons Inc. installed 21,467 linear feet of 12-inch steel pipeline to expand capacity between two existing stations.
Expansions & Modifications
Pipeline
TEXAS
16″ Pipeline Facility Interconnect
Evers & Sons Inc. installed 8,346 linear feet of 16-inch steel pipeline to connect a central processing facility to existing pipeline infrastructure.
Interconnects & Connections
Pipeline
TEXAS
6″ Pipeline Well Connection
Evers & Sons Inc. installed 1,200 linear feet of 6-inch steel pipeline to support a new well connection to existing infrastructure.
Interconnects & Connections
Pipeline
TEXAS
Pipeline Recommissioning
Evers & Sons Inc. removed an existing 12-inch launcher and performed cleaning pig runs and caliper tool inspections within a previously decommissioned pipeline.