Facility Demolition: Central Tank Battery
Demolition
Project Overview
Demolition and Equipment Removal
- Demolished all buildings and structures on site, including:
- (1) 3516 compressor
- (1) Dehydration unit
- (5) 1,000-barrel water tanks and five 1,000-barrel oil tanks
- (4) Process trains, each including:
- Heater treater
- 3-phase separator
- LACT units
- Inlet manifold skid
- (8) Daniel Junior meter runs
- 75′ flare, flare scrubber, and flare knockout drums
- Recirculation pumps, water transfer pumps, skid-mounted air compressor, and a 1250 KVA transformer
Site-Wide Removals
- Removed all buried and above-ground infrastructure, including:
- Piping, electrical wiring, conduit, and foundations
- Electrical and instrumentation equipment servicing the site or battery, such as motors, generator panel boards, transformers, lighting, control panels, transmitters, and gauges
- Oil storage tanks, accessory tanks, secondary containment, air tanks, and utility water storage tanks
Material and Fluid Handling
- Drained and disposed of all fluids remaining in piping and structures
- Properly removed and disposed of produced water, residual oil, and any contaminated materials, including soil, gravel, asphalt, hydrovac materials, and excess excavation debris
- Vented all gas piping and de-energized all systems before demolition
- Confirmed disconnection of utilities (mechanical, electrical, and process) prior to commencing work
Site Preparation and Restoration
- Compacted all fill dirt areas in lifts to meet project requirements
- Installed soil erosion and sediment control barriers (SWPP measures) before any ground disturbance activities
- Removed all concrete foundations, above-grade steel supports, and any additional site-specific structural components