Meter and Regulator Station

Metering & Regulation

Project Overview

This project included full civil sitework and the installation of concrete foundations to support major facility components. Key equipment included a meter skid, regulator skid, and line heater. Our scope also included the in-house fabrication and installation of 16-inch interconnecting piping, complete I&E installation, and final site fencing.

Components Installed:

  • 2,700 CY of spoil removal
  • 2,776 CY of select fill install
  • 88 CY of concrete foundations
  • Setting of meter skid, regulator skid and line heater
  • 1,940 weld inches

Additional Scope:

  • Fabrication and installation of structural platforms and supports for the skidded equipment
  • Commissioning of the facility to receive gas

Functionality:

Designed and installed to receive natural gas from the distribution point and meter to the end user to operate their semiconductor plant