Project Overview
Evers & Sons provided full field installation services for the Gillis Treating Plant, a core component of Momentum Midstream’s NG3 Project— a 1.7 Bcf/d natural gas processing plant linking the Haynesville Shale to Gulf Coast LNG markets.
Amine System – Key Equipment (Per Train):
- (3) Amine Contactors
- (3) Treated Gas Coolers
- (3) Inlet Skids
- (3) Amine Circulation Pumps
- (6) Lean Amine Coolers
- (1) Amine Flash Drum
- (1) Amine Charcoal Filter
- (1) Reflux Skid
- (1) Amine Surge Tank
- (3) Heat Medium Heaters
- (2) Amine Reboilers
- (2) Regen Still Towers
- (4) Reflux Condensers
BOP Mechanical Equipment – Key Equipment:
- (1) Inlet Separator
- (8) TEG Dehy Packages
- (5) CO₂ Screw Compressors | (2) CO₂ Recip Compressors
- (2) CO₂ Dehy Packages | (4) BTEX Scrubber/Cooler Packages
- (1) Flare
- (1) BTEX Flare
- (1) RO Water Treatment System | (1) Instrument Air Skid
- (1) 210 BBL Amine Storage Tank | (5) 750 BBL Closed Drain Tanks
- (3) 750 BBL Raw Water Tanks | (3) 750 BBL RO Water Tanks
- (3) Cummins Powered Backup Generators
- (3) PDC Buildings
Scope of Work:
- Installation of ± 60,000 LF of prefabricated pipe (2”–36”)
- ± 145,617 field weld inches
- ± 5,791 pre-fabricated pipe spools
- ± 20,000 LF of interconnect piping
- ± 570 tons of structural steel fabrication and erection
- ± 1,500 CY of concrete
- Flange torquing (4,355 flanges)
- QA/QC management and job books
- Oversight of I&E partner
Additional Scope:
- Turnkey Sub Station Construction
- Control Room & Office Building
- Warehouse
This greenfield facility serves as the core of NG3’s carbon capture and gas treating system, integrating CO₂ amine treating, dehydration, and compression to deliver clean natural gas while maintaining a net-negative CO₂ emission profile.
Evers & Sons provided full field installation services for the Gillis Treating Plant, including construction of an 8,000 GPM amine treating facility, a core component of Momentum Midstream’s NG3 Project linking the Haynesville Shale to Gulf Coast LNG markets. The facility was originally designed for 1.7 Bcf/d of throughput, with the expansion incorporating additional equipment to increase total processing capacity to approximately 2.3 Bcf/d.
PHASE I:
Amine System – Key Equipment (Per Train):
- (3) Amine Contactors
- (3) Treated Gas Coolers
- (3) Inlet Skids
- (3) Amine Circulation Pumps
- (6) Lean Amine Coolers
- (1) Amine Flash Drum
- (1) Amine Charcoal Filter
- (1) Reflux Skid
- (1) Amine Surge Tank
- (3) Heat Medium Heaters
- (2) Amine Reboilers
- (2) Regen Still Towers
- (4) Reflux Condensers
BOP Mechanical Equipment – Key Equipment:
- (1) Inlet Separator
- (8) TEG Dehy Packages
- (5) CO₂ Screw Compressors | (2) CO₂ Recip Compressors
- (2) CO₂ Dehy Packages | (4) BTEX Scrubber/Cooler Packages
- (1) Flare
- (1) BTEX Flare
- (1) RO Water Treatment System | (1) Instrument Air Skid
- (1) 210 BBL Amine Storage Tank | (5) 750 BBL Closed Drain Tanks
- (3) 750 BBL Raw Water Tanks | (3) 750 BBL RO Water Tanks
- (3) Cummins Powered Backup Generators
- (3) PDC Buildings
Scope of Work:
- Installation of ± 60,000 LF of prefabricated pipe (2”–36”)
- ± 152,171 field weld inches
- ± 7,500 pre-fabricated pipe spools
- ± 800 tons of structural steel fabrication and erection
- ± 2,900 CY of concrete
- Flange torquing (5,275 flanges)
- QA/QC management and job books
- Oversight of I&E partner
- Number of welds: ±6,200
Additional Scope:
- Turnkey Sub Station Construction
- Control Room & Office Building
- Warehouse
PHASE II: Expansion Scope
- (2) 5000 HP Electric Drive Residue Compression – (Residue compression increases capacity to 2 Bcf/d)
- (2) H2S Treating Units for CO₂ Stream Treating
- (1) CO₂ TEG Dehydration Unit
This greenfield facility serves as the core of NG3’s carbon capture and gas treating system, integrating CO₂ amine treating, dehydration, and compression to deliver clean natural gas while maintaining a net-negative CO₂ emission profile.
Download Project Sheet
Let's partner on your next project.