Gillis Amine Plant: Phase I and II

LOUISIANA

Project Overview

Evers & Sons provided full field installation services for the Gillis Treating Plant, a core component of Momentum Midstream’s NG3 Project— a 1.7 Bcf/d natural gas processing plant linking the Haynesville Shale to Gulf Coast LNG markets.

Amine System – Key Equipment (Per Train):

  • (3) Amine Contactors
  • (3) Treated Gas Coolers
  • (3) Inlet Skids
  • (3) Amine Circulation Pumps
  • (6) Lean Amine Coolers
  • (1) Amine Flash Drum
  • (1) Amine Charcoal Filter
  • (1) Reflux Skid
  • (1) Amine Surge Tank
  • (3) Heat Medium Heaters
  • (2) Amine Reboilers
  • (2) Regen Still Towers
  • (4) Reflux Condensers

BOP Mechanical Equipment – Key Equipment:

  • (1) Inlet Separator
  • (8) TEG Dehy Packages
  • (5) CO₂ Screw Compressors | (2) CO₂ Recip Compressors
  • (2) CO₂ Dehy Packages | (4) BTEX Scrubber/Cooler Packages
  • (1) Flare
  • (1) BTEX Flare
  • (1) RO Water Treatment System | (1) Instrument Air Skid
  • (1) 210 BBL Amine Storage Tank | (5) 750 BBL Closed Drain Tanks
  • (3) 750 BBL Raw Water Tanks | (3) 750 BBL RO Water Tanks
  • (3) Cummins Powered Backup Generators
  • (3) PDC Buildings

Scope of Work:

  • Installation of ± 60,000 LF of prefabricated pipe (2”–36”)
  • ± 145,617 field weld inches
  • ± 5,791 pre-fabricated pipe spools
  • ± 20,000 LF of interconnect piping
  • ± 570 tons of structural steel fabrication and erection
  • ± 1,500 CY of concrete
  • Flange torquing (4,355 flanges)
  • QA/QC management and job books
  • Oversight of I&E partner

Additional Scope:

  • Turnkey Sub Station Construction
  • Control Room & Office Building
  • Warehouse

This greenfield facility serves as the core of NG3’s carbon capture and gas treating system, integrating CO₂ amine treating, dehydration, and compression to deliver clean natural gas while maintaining a net-negative CO₂ emission profile.

Evers & Sons provided full field installation services for the Gillis Treating Plant, including construction of an 8,000 GPM amine treating facility, a core component of Momentum Midstream’s NG3 Project linking the Haynesville Shale to Gulf Coast LNG markets. The facility was originally designed for 1.7 Bcf/d of throughput, with the expansion incorporating additional equipment to increase total processing capacity to approximately 2.3 Bcf/d.

PHASE I:

Amine System – Key Equipment (Per Train):

  • (3) Amine Contactors
  • (3) Treated Gas Coolers
  • (3) Inlet Skids
  • (3) Amine Circulation Pumps
  • (6) Lean Amine Coolers
  • (1) Amine Flash Drum
  • (1) Amine Charcoal Filter
  • (1) Reflux Skid
  • (1) Amine Surge Tank
  • (3) Heat Medium Heaters
  • (2) Amine Reboilers
  • (2) Regen Still Towers
  • (4) Reflux Condensers

BOP Mechanical Equipment – Key Equipment:

  • (1) Inlet Separator
  • (8) TEG Dehy Packages
  • (5) CO₂ Screw Compressors | (2) CO₂ Recip Compressors
  • (2) CO₂ Dehy Packages | (4) BTEX Scrubber/Cooler Packages
  • (1) Flare
  • (1) BTEX Flare
  • (1) RO Water Treatment System | (1) Instrument Air Skid
  • (1) 210 BBL Amine Storage Tank | (5) 750 BBL Closed Drain Tanks
  • (3) 750 BBL Raw Water Tanks | (3) 750 BBL RO Water Tanks
  • (3) Cummins Powered Backup Generators
  • (3) PDC Buildings

Scope of Work:

  • Installation of ± 60,000 LF of prefabricated pipe (2”–36”)
  • ± 152,171 field weld inches
  • ± 7,500 pre-fabricated pipe spools
  • ± 800 tons of structural steel fabrication and erection
  • ± 2,900 CY of concrete
  • Flange torquing (5,275 flanges)
  • QA/QC management and job books
  • Oversight of I&E partner
  • Number of welds: ±6,200

Additional Scope:

  • Turnkey Sub Station Construction
  • Control Room & Office Building
  • Warehouse

PHASE II: Expansion Scope

  • (2) 5000 HP Electric Drive Residue Compression – (Residue compression increases capacity to 2 Bcf/d)
  • (2) H2S Treating Units for CO₂ Stream Treating
  • (1) CO₂ TEG Dehydration Unit

This greenfield facility serves as the core of NG3’s carbon capture and gas treating system, integrating CO₂ amine treating, dehydration, and compression to deliver clean natural gas while maintaining a net-negative CO₂ emission profile.

Download Project Sheet

Image
Contact Information

[email protected]
www.eversandsons.com
(979) 596-2139
(800) 552-1236

Let's partner on your next project.