Project Overview
Evers & Sons provided full field installation services for a 100 MMSCFD brownfield compressor station in Louisiana. The project included concrete, structural steel, mechanical piping, and facility painting to support the installation of prefabricated compressor packages and associated fuel gas and filtration systems. Work was executed within an active facility environment while integrating new compression infrastructure to enhance system capacity and reliability.
Key Equipment:
- (2) 3606 Compressor Skid Packages (prefabricated)
- (2) Discharge Coalescing Filters
- Fuel Gas Skid
Scope of Work:
- Concrete
- Structural Steel
- Mechanical Piping
- Facility Painting
Field Installation – Stats:
- ±70 cubic yards concrete
- ±8 tons structural steel
- ±3,500 linear ft. pipe – from 1” to 30”
- 699 welds
- ±11,000 field weld inches
- 243 flange torques