Project Overview
Evers & Sons completed the installation of 10,471 linear feet of 8-inch steel pipeline to expand takeaway capacity for high-H₂S gas from the existing system. The project included multiple road and utility crossings, including county road bores and a 1,700-linear-foot horizontal directional drill beneath a state highway and railroad. Scope of work also included installation of prefabricated launcher and receiver assemblies, an 8-by-12-inch hot tap with associated piping, fabrication and installation of a 6-inch meter run, construction of a 100 x 100 surface site, and development of two permanent access roads. All work was executed to support safe system integration while maintaining operational and environmental requirements.
Length & Configuration:
Installation of 10,471 linear feet of 8″ steel pipeline
Components Installed:
- 800 liner feat of county road bores and one 1700 LF HDD of a state highway and railroad
- Installation of one each 8’’ prefabricated launcher and receiver
- Installation of an 8×12’’ hot tap and associated piping
- Fabrication and installation of one 6’’ meter and associated piping
- Construction of a 100 x 100 surface site
- Construction of two permanent access roads
Functionality:
The project expanded takeaway capacity to safely accommodate high-H₂S gas from the existing system.